Cobb Commissioner: Residents Pleased with Roundabout

The project at Holly Springs and Davis roads was completed this summer.

Although East Cobb residents weren't sure what to think about a roundabout being installed at the intersection of Holly Springs and Davis roads, District 3 Commissioner Joann Birrell said during Tuesday night's Board of Commissioner's meeting that she has heard nothing but positive feedback since the project was finished.

"Not everyone was sure about it when we started," Birrell said. "It's been a great improvement."

The Board of Commissioners on Tuesday approved a final change order for the project with a savings of roughly $47,500.

Find out what's happening in West Cobbwith free, real-time updates from Patch.

The project was an intersection safety and operational improvement project included in the 2011 SPLOST. In February, the board approved a contract with C.W. Matthews Contracting Company to remove the previous multi-way stop, and design and construct the roundabout.

The board approved five other transportation items, including awarding a contract with ECS Southeast for geotechnical engineering for bridge replacements on Pitner Road over Little Allatoona Creek and Paper Mill Road over Sope Creek. The contract amounts are not to go over $20,000 and $27,560, respectively, and include a bridge foundation investigation and a geotechnical engineering assessment at both locations.

Find out what's happening in West Cobbwith free, real-time updates from Patch.

In a related matter, the board approved a contract with AECOM Technical Services for engineering design of the bridge replacement on Paper Mill Road over Sope Creek at a cost not to exceed $217,273.80.

Commissioner Bob Ott said the original bridge was built in 1920, and the county has performed numerous maintenance projects on it. The replacement project originally was planned for the 2005 SPLOST but is being moved to the 2011 SPLOST since most of the original funding already has been expended on the structure.

In other business, the board voted to authorize a selection committee to negotiate scope, fees, and contract terms and conditions for architectural and engineering services related to new construction and renovation work at the Cobb County Health Department. The work is being funded through the 2011 SPLOST and is slated to being at the end of 2013 or beginning of 2014.

Don’t miss any of the local news you care about. Subscribe to West Cobb Patch’s free newsletterlike us on Facebook and follow us on Twitter.

We’ve removed the ability to reply as we work to make improvements. Learn more here

The views expressed in this post are the author's own. Want to post on Patch?

More from West Cobb